asked the Minister for Education if she will make a statement on the present position in relation to the buildings and extensions applied for by the City of Galway Vocational Education Committee and the County of Galway Vocational Education Committee; the date of such applications; their present stage; and in each case, the dates of approval within her Department.
Written Answers. - Galway VEC Buildings and Extensions.
The information requested by the Deputy is as follows:
Committee |
School |
Date of Application |
Date of original approval of project |
Present Stage of Architectural Planning |
City of Galway VEC |
Fr. Griffin Road VS |
July 1981 |
February 1982—Extension to enable school to cater for 500 pupils |
Stage 1(Site Report) Completed |
County Galway Vocational Education Committee |
Inverin VS |
September 1981 |
October 1982—Extension to enable school to cater for 100 pupils |
Stage 5(Bills of Quantities) |
Gort VS |
May 1980 |
March 1982—Extension to enable school to cater for 175 pupils |
Stage 3(Developed Sketch Scheme) being examined |
|
New Inn VS |
May 1980 |
May 1981—Extension to enable school to cater for 150 pupils |
Stage 5(Bills of Quantities) |
|
Portumna VS |
July 1979 |
March 1982—Extension to enable school to cater for 175 pupils |
Stage 5(Bills of Quantities) Completed |
|
Athenry VS |
October 1983 |
January 1981—Extension to enable school to cater for 525 pupils |
State 3(Developed Sketch Scheme) |
|
Ballinasloe VS |
July 1979 |
December 1980—Extension to enable school to cater for 275 pupils |
Stage 4(Working Drawings) |
|
Tuam VS |
Original application received in Department in May 1975 |
July 1980—New School for 300 pupils |
Stage 5(Bills of Quantities) |